HA. Ihavandhoo Council

Goal 4

Environment and energy

Sewerage, waste management and solar energy.

Goal progress

Targets

  • 01Sewerage network by 2027
  • 02Mosque solar
Average progress of linked projects51%

Linked projects

Projects that deliver this goal.

All projects
  • Ongoing
    Government projects (PSIP)

    Sewerage network

    Constructing the island sewerage network.

    Progress24%
    Budget
    MVR 46,000,000
    Government PSIP
    Spent: MVR 11,040,000 · 24% of budget spent
    Start
    1 March 2026
    Expected end
    30 June 2027
  • Ongoing
    Council projects

    Mosque solar panels

    Installing solar panels at the mosque.

    Progress85%
    Budget
    MVR 598,000
    Council budget
    Spent: MVR 508,300 · 85% of budget spent
    Start
    20 September 2026
    Expected end
    30 November 2026
  • Delayed
    Council projects

    Waste sorting centre

    A covered centre to sort recyclables before shipment.

    Progress45%
    Budget
    MVR 1,200,000
    Council budget
    Spent: MVR 480,000 · 40% of budget spent
    Start
    1 February 2026
    Expected end
    30 September 2026

    Overdue by 21 days