HA. Ihavandhoo Council

Projects

Track council, government and WDC projects.

Total budget
MVR 222.6M
Spent to date
MVR 86.1M
Ongoing
5
Completed
2
Delayed / postponed
2
Halted
2
Development listThe development plan, how it is carried out and the Secretariat's planned work.

12 results

Ongoing
Government projects (PSIP)

Harbour upgrade

Expanding and upgrading the harbour for vessels and fish landing.

Progress62%
Budget
MVR 38,000,000
Government PSIP
Spent: MVR 23,560,000 · 62% of budget spent
Start
1 March 2025
Expected end
31 December 2026
Delayed
Government projects (PSIP)

25-hectare land reclamation

Reclamation of 25 hectares with a 1,080 m revetment and an 80 m groyne.

Progress38%
Budget
MVR 104,700,000
Government PSIP
Spent: MVR 39,786,000 · 38% of budget spent
Start
1 June 2025
Expected end
30 September 2026

Overdue by 21 days

Planned
Government projects (PSIP)

Cold storage facility

Building a cold storage facility to keep processed fish products.

Progress5%
Budget
MVR 18,500,000
Government PSIP
Spent: MVR 0 · 0% of budget spent
Start
15 January 2027
Expected end
31 December 2027
Ongoing
Council projects

Road paving (phase 2)

Second phase of island road paving.

Progress71%
Budget
MVR 1,795,000
Council budget
Spent: MVR 1,260,000 · 70% of budget spent
Start
15 June 2026
Expected end
15 December 2026
Completed
Council projects

School hall

Construction of a school multipurpose hall.

Progress100%
Budget
MVR 2,400,000
Council budget
Spent: MVR 2,385,600 · 99% of budget spent
Start
1 September 2025
Completed
14 July 2026
Ongoing
Government projects (PSIP)

Sewerage network

Constructing the island sewerage network.

Progress24%
Budget
MVR 46,000,000
Government PSIP
Spent: MVR 11,040,000 · 24% of budget spent
Start
1 March 2026
Expected end
30 June 2027
Ongoing
WDC projects

Women's craft centre

A centre where women make and sell handicrafts.

Progress55%
Budget
MVR 950,000
Council budget and WDC
Spent: MVR 522,500 · 55% of budget spent
Start
1 August 2026
Expected end
31 January 2027
Ongoing
Council projects

Mosque solar panels

Installing solar panels at the mosque.

Progress85%
Budget
MVR 598,000
Council budget
Spent: MVR 508,300 · 85% of budget spent
Start
20 September 2026
Expected end
30 November 2026
Completed
Government projects (PSIP)

Health centre extension

Two new consultation rooms and a small laboratory added to the island health centre.

Progress100%
Budget
MVR 6,200,000
Government PSIP
Spent: MVR 6,050,000 · 98% of budget spent
Start
1 February 2025
Completed
22 April 2026
Halted
Council projects

Community park

A shaded park with a children's play area at the western end of the island.

Progress28%
Budget
MVR 1,450,000
Council budget
Spent: MVR 410,000 · 28% of budget spent
Start
1 March 2026
Expected end
30 November 2026
Halted
Council projects

Football ground floodlights

Floodlights for evening matches and training.

Progress15%
Budget
MVR 780,000
Council budget
Spent: MVR 120,000 · 15% of budget spent
Start
15 May 2026
Expected end
15 October 2026

Overdue by 6 days

Delayed
Council projects

Waste sorting centre

A covered centre to sort recyclables before shipment.

Progress45%
Budget
MVR 1,200,000
Council budget
Spent: MVR 480,000 · 40% of budget spent
Start
1 February 2026
Expected end
30 September 2026

Overdue by 21 days